ECJ 17 March 2021, Case C-585/19 (Academia de Studii Economice din Bucureşti), Working Time

Academia de Studii Economice din Bucureops ti – v – Organismul Intermediar pentru Programul Operaţional Capital Uman – Ministerul Educaţiei Naţionale, Romanian Case

Keywords Working Time
DOI
Show PDF Show fullscreen
Abstract Statistics Citation
This article has been viewed times.
This article been downloaded 0 times.
Suggested citation
, "ECJ 17 March 2021, Case C-585/19 (Academia de Studii Economice din Bucureşti), Working Time", European Employment Law Cases, 1, (2021):74-75

    Where a worker has concluded more than one employment contract with the same employer, the minimum daily rest period applies to the contracts taken as a whole and not to each of the contracts taken separately.

Dit artikel wordt geciteerd in

    • Summary

      Where a worker has concluded more than one employment contract with the same employer, the minimum daily rest period applies to the contracts taken as a whole and not to each of the contracts taken separately.

    • Question

      Must Article 2(1) and Article 3 of Directive 2003/88 be interpreted as meaning that, where an employee has concluded several contracts of employment with the same employer, the minimum daily rest period provided for in Article 3 applies to those contracts taken together or to each of those contracts taken separately?

    • Ruling

      Articles 2(1) and 3 of Directive 2003/88/EC of the European Parliament and of the Council of 4 November 2003 concerning certain aspects of the organisation of working time must be interpreted as meaning that, where an employee has concluded several contracts of employment with the same employer, the minimum daily rest period provided for in Article 3 thereof applies to those contracts taken as a whole and not to each of those contracts taken separately.